Shotcrete Use in Underground Construction

Since the mid-2000s, shotcrete usage in underground construction has soared because contractors can install it more quickly and efficiently than traditional cast-in-place concrete systems. Project teams have supported adoption of the technology based on what has been described as a meaningful schedule acceleration of the time typically required to complete a foundation. For large-scale projects, that can translate into millions of dollars through accelerated occupancy and timely project completion. Enabling this surge in shotcrete use are advancements in waterproofing systems designed specifically for the material.

Below-grade construction with cast-in-place concrete requires installing forms in the excavation, pouring concrete, waiting for it to cure, and finally removing all the forms. Shotcrete application is typically faster because it can be done quickly by qualified nozzle operators without the need for concrete formwork. However, it does come with its own set of risks.

For example, shotcrete use can lead to voids in concrete walls and behind rebar. These problems, in turn, allow water to migrate around and into a structure should the waterproofing system fail. Water migration can derail timely project completion at great cost, while exposing the structure to leaks and flooding over its useful life. Also, the force of shotcrete spray can damage waterproofing membranes, as can the impact of adjacent building construction and flaws introduced by rebar, electrical, or plumbing contractors.

HIGH-PERFORMANCE WATERPROOFING SYSTEM

When first working with shotcrete, contractors tried adapting pre-applied waterproofing solutions traditionally used with cast-in-place applications to shotcrete projects. After shotcrete placement onto the waterproofing membrane, contractors were forced to seal leaks by drilling holes through the shotcrete wall in trouble spots and injecting grout. As contractors could not see or track the pattern or extent of the vulnerability, the only method of filling the void or defect with grout was timeconsuming trial and error. This blindside approach produced only limited success or outright failure.

One solution to these deficiencies is use of an effective shotcrete waterproofing system, comprised of a membrane, grout-injection tubes, and grout. A tough composite membrane can stand up to the force and application of shotcrete, while a polymer-mesh-reinforced cavity sits between a layer of plastic film and a nonwoven, semipermeable geotextile.

In step one of the application process, the contractor attaches the membrane to the soil retention wall—typically a combination of piles and lagging. Before applying the shotcrete, the contractor fastens a spaced matrix of injection tubes onto the geotextile of the membrane. In step two, the grout is injected through the tubes after the shotcrete wall has cured. This can be one to two months after the construction of the wall and is a process that can be completed as construction on the project moves beyond the foundation (allowing for schedule acceleration).

During injection, the reactive grout fills the cavity created by the membrane and permeates through the geotextile. As a result, it forms a monolithic curtain wall of grout, proactively sealing voids in the wall itself and creating a high-performance waterproofing system bonded to the shotcrete.

This two-step method stops leaks before they happen, ensuring construction stays on schedule, liabilities are minimized, and the waterproofing solution shields the structure from water infiltration throughout the design life of the project. Combining preapplied membrane technology with injected leak-sealing materials results in a fully integrated waterproofing system. With this type of technology at their disposal, engineers and general contractors are increasingly turning to shotcrete to accelerate their high-profile, high-risk projects.

REBUILDING MAJOR HIGHWAY SYSTEM

The Alaskan Way Viaduct in Seattle is a north-to-south traffic corridor that carries tens of thousands of commuters through the city daily. Built as a bridge in 1953, the viaduct was damaged in 2001 by an earthquake. In 2013, construction crews began replacing it with a 2-mile long tunnel beneath the city at a projected cost of $4.5 billion.

The tunnel’s north and south portals span about 2,000 ft and start at grade before plunging about 80 ft deep. Adding to the complexity, multiple highway lanes merge into different levels of the tunnel. Further, the jobsite sits at sea level in a city known for its extremely wet climate.

Waterproofing of the viaduct began in June 2013. The waterproofing contractors installed about 350,000 sf of shotcrete waterproofing, or 600,000 sf of waterproofing membrane in total. In addition to protecting the viaduct, an additional 150,000 sf of membrane was utilized on the portals and the viaduct’s operations buildings. Multiple systems were employed to accommodate the use of both shotcrete and cast-in-place concrete.

Despite soaking rains and leaky ground, the team completed the project in 2016, on time and without incident. Field engineers were onsite throughout the waterproofing process, ensuring proper installation of the waterproofing systems, training contractors, and troubleshooting any issues.

TACKLING THE CHALLENGE

In 2014, general contractor Turner Construction was tasked with building the Golden 1 Center, new home to the National Basketball Association’s (NBA’s) Sacramento Kings. The owners gave Turner less than 2 years to complete the 17,500-seat, $507-million arena.

Turner chose F.D. Thomas as the waterproofing contractor to take on the challenges of a stadium that sits below the water table and is adjacent to two major rivers. For its waterproofing system, the contractor selected an integrated waterproofing membrane.

Rainstorms dumped 3 ft of water on the excavation before F.D. Thomas began the installation. Despite the flooding, the contractor completed the job in just 45 days. Stuart Hunter, vice-president of F.D. Thomas’s waterproofing division, credits his colleagues, the teamwork of Turner, and the concrete, rebar, and plumbing subcontractors—as well as the waterproofing system—for executing the task under pressure and finishing 15 days early. Since opening in September 2016, Golden 1 Center has operated without interruption due to leaks or flooding.

CONCLUSION

Advancements in waterproofing have enabled the rapid growth of shotcrete usage in traditional structural applications. With this type of technology available, contractors, designers, installers, and engineers will continue to expand the use of shotcrete, reaping the associated schedule benefits.

 

About the author:

Greg Austin is the global product director, specialty building materials, for GCP Applied Technologies. Based in Cambridge, Massachusetts, he has a background in consulting and more than 5 years of experience in waterproofing system development and construction materials. Austin can be reached via e-mail at greg.austin@gcpat.com.

Xia Cao is principal scientist at GCP Applied Technologies. She has more than 12 years of experience in waterproofing system and building materials development, and more than 20 years in material science and process engineering. She can be reached via e-mail at xia.cao@gcpat.com.

____________________________________________________
Modern Contractor Solutions, November 2018
Did you enjoy this article?
Subscribe to the FREE Digital Edition of Modern Contractor Solutions magazine.
BUTTON_ClickHere