Building permit problems can delay new warehouse construction or distribution center retrofits by weeks or months. Bringing in an experienced warehouse storage rack supplier early in the process can help facility managers avoid being blindsided by building permit delays and help keep operation plans on track. The right warehouse rack storage system supplier can help prevent permit headaches by providing comprehensive building permit services.
THE ISSUE
According to a material handling permit expeditor servicing the western United States in the material handling equipment industry, permits are required but not limited to storage rack, pallet rack, rack picking systems, conveyor systems, and mezzanine/storage platforms used in warehouses and home improvement centers.
While the permit process usually takes from 3 to 6 weeks from beginning to end, it can take as long as 16 weeks. Each city, county, and state have their own ordinances that must be met, and some cities require full compliance with the Federal Americans with Disabilities Act (ADA) before issuing a permit.
A few common layout errors to avoid include “dead end” aisles, rack systems blocking doorways, and a lack of aisle space.
MINIMUM REQUIREMENTS
At a minimum, a simple rack permit in a state such as California requires detail drawings of the storage rack base plates, columns/post attachments and the anchors used. In California, this requirement applies even to equipment from 5 ft, 11 inches to 8 ft tall, though there are exceptions.
A regular rack permit is required in all U.S. states when storage rack equipment exceeds 8 ft in height, per International Building Code standards. Structural calculations by a civil or structural engineer, registered in the state where the work is done, is then required along with component detail drawings. Project drawings showing a complete floor plan, along with cross sectional views plus connection details of the project, and a facility site plan are typically necessary for submittal. Permit fees include a plan check submittal fee, permit issuance fee, and a fire department approval fee. These fees are usually required, along with a state licensed contractor-installer.
An error in any of these steps, of course, translates into costly permit and operational delays.
MEETING FIRE CODE
Fire codes can be a particular problem. Building departments will not release the storage rack permit until you provide them with Fire Department High Pile Storage (HPS) approval. Most rack permit delays are due to poor HPS approval planning.
Even if a facility has a building permit, there will still be a fire permit inspection. This can involve sprinklers, vents, firewalls, access to exits, and hydrants. A facility’s needs can be especially complicated if there are pick systems or elevated work areas. If the facility manager misses any of these local requirements, the fire marshal may not allow building occupancy.
THE SOLUTION
The key is to start the permit process as soon as possible and get it right the first time. That way, facility managers won’t have to wait on pins and needles for a municipal building or fire department to get back to them—with requests for more documentation that can require resubmission two, three, four, or more times.
To help facility managers avoid permit delays and keep operation plans on track, some suppliers of warehouse rack storage systems, such as Steel King Industries, prevent permit headaches by providing comprehensive building permit services. For instance, the company offers a calculation package for the permit process, and deals with all national, regional, or local agents necessary to handle permitting. It accomplishes this with in-house professional engineering staff and a network of permit specialists.
“With seismic codes enforced nationally but with variations by locale, facility managers need a company that understands the permit process with the resources to stay on top of it,” says Steel King project coordinator Anne Russell. Steel King, a major designer and manufacturer of warehouse storage racks, pallet racks and material handling/safety products, has helped plan warehouses since 1970. It is a licensed fabricator in Los Angeles County, which has some of the strictest seismic codes in the nation.
The Rack Manufacturers Institute (RMI) publishes a racking design specification and the American Iron and Steel Institute (AISI) and American Institute of Steel Construction (AISC) each publish a steel design specification. The racking system must be compliant with these specifications along with local building and fire codes.
CLOSING THOUGHT
A good way to expedite the permit process is to work with a reputable storage rack manufacturer such as Steel King, which can supply or coordinate the engineering and layout details in a turnkey permit package.
For More Information:
For more on easing the permit burden, call Steel King at 800.826.0203 or visit www.steelking.com.
Modern Contractor Solutions, March 2023
Did you enjoy this article?
Subscribe to the FREE Digital Edition of Modern Contractor Solutions magazine.