Constructing a cast-in-place pump station is nothing new for J & K Contracting of Ames, Iowa. However, constructing a cast-in-place pump station inside of Iowa State University’s Jack Trice Stadium, less than a first down’s length away from the southern end zone, is certainly something new.
THE PROJECT
The project is part of the Jack Trice Stadium South End Zone Project, a $60 million project that will add capacity and a High Definition video board. Upon completion of this project, prior to the start of the 2015 college football season, Jack Trice Stadium will be the third largest football stadium in the Big 12 conference.
For its part, J & K Contracting won the bid to build the new pump station. The new station is designed to handle more stormwater and will replace an older, undersized station.
“Time was a concern on this project,” notes Matt Runge, chief operating officer at J & K Contracting. “The job requirements demanded a shoring system that could be installed and removed to accommodate a very compressed schedule.”
The system J & K had in mind was a Slide Rail System, a dig and push style system. With its modular, flexible design, the system can comply with a wide variety of shapes and sizes. Installed from the top down and removed from the bottom up, it minimizes size of excavations, soil disturbances, restoration time, and cost. The installation is done with low vibration, providing soil support for excavations, adjacent structures, and existing utilities.
THE SOLUTION
“Upon hearing that they had been awarded the bid for the project, I contacted Matt at J & K,” remarks Dave Hehr, president of Contractor Solutions Trench Shoring, Pro-Tec Equipment’s distributor in Iowa. “I knew going in to the meeting that a Slide Rail System would be the best way to go on this job. With the limited working area, and being just feet away from the Jack Trice Football Field Turf, Slide Rail seemed like a perfect fit. We had worked with J & K previously, using the Pro-Tec Equipment Slide Rail system. Unfortunately, they thought the posts of the system were too tight with their tracked design compared to other systems on the market,” adds Dave. “I contacted Pro-Tec Equipment about it, speaking with Josh Brown (Pro-Tec Equipment Slide Rail specialist/inside sales). We spoke about how we might be able to fix that problem for them; his suggestion was their new Gen II posts.”
The Pro-Tec Equipment Slide Rail System Gen II Posts, designed initially for use by Latin American contractors, which typically use smaller, lighter weight excavators, are lighter and easier to handle when compared to the Gen I Posts.
“As a result of the positive feedback we received, we decided that the Gen II posts would be made available within North America as well,” adds Joshua Thorne, Pro-Tec Equipment Slide Rail manager.
“In talking with Dave, the Gen II posts seemed to be the answer to the issues that J & K had with our Slide Rail System,” comments Brown. “The way the posts are designed, they allow for more play between the posts and panels, while still ensuring that the panels are securely in place. This allows the posts and the overall system to be to be installed and removed with a bit more ease, compared to our Gen I posts.”
The Pro-Tec Equipment Slide Rail System Gen II Posts are built to accommodate 24 feet of panel height, with an overall post height of 22 feet for both the Corner and Spreader (Linear) Post. Using a combination of the tight track design for the outer track (used throughout the Gen I post), and a more open, slot track design for the inner track, the Gen II posts enables the Pro-Tec Equipment Slide Rail System to achieve 20 feet deep clear span systems without having to use larger, heavier post.
“After talking with Josh Brown, I had the meeting with J & K, in which I was able to show them actual photos of the post and CAD drawings done by Pro-Tec Equipment’s in-house CAD Staff. They (J & K) said they would try it,” recounts Dave.
THE INSTALLATION
Using a John Deere 450 excavator and a Hitachi 85, J & K Contracting was able to install the Slide Rail System, measuring 34 feet, 6 inch ID long by 21 feet ID wide, by 16 feet deep. With the aid of Carl Leonard, one of Pro-Tec Equipment’s trained Slide Rail Site consultants, the system was installed in a matter of 2 days.
“The new Gen II posts have improved tremendously from the Gen I enabling a more effortless installation and removal process,” notes Matt.
As a testament to the Pro-Tec Equipment Slide Rail Systems flexibility, the system was originally designed and sent to the site as a clear span system; however, site conditions and job requirements dictated an on-the-fly change.
“Once we came on site, we saw that clear spanning the system would not be needed,” notes Brown. “J & K was actually able to achieve the vertical clearance they desired by bracing the spreader post off the poured pad and raising the spreader assembly up, saving them additional time and expense.”
“The Contractor Solutions/Pro-Tec Equipment team is second to none when it comes to equipment delivery, assistance in set up, and customer service,” adds Matt. “We look forward to a continued partnership with this team and many more successful projects to come.” ■
For More Information: Tommy Marciniak is the marketing manager for Trinity Shoring Products, Inc. Pro-Tec Equipment has been a leading producer and distributor of trench shield and trench shoring products since 1995. Contact Pro-Tec Equipment at 800.292.1225, or visit www.pro-tecequipment.com.
_________________________________________________________________________
Modern Contractor Solutions, May 2015
Did you enjoy this article?
Subscribe to the FREE Digital Edition of Modern Contractor Solutions magazine.