California-based developers Baldwin & Sons began the design and development of a housing complex on 99 acres of land in the city of Lake Forest, at the base of the Santa Ana Mountains, in 2014. About two-thirds complete, the 931-unit development, The Oaks at Portola Hills, is comprised of seven neighborhoods of both single-family and multi-family residences, and sits at the edge of the Limestone Whiting Ranch Wilderness Park, one of Orange County’s largest wilderness preserves.

Developing Portola Hills required converting the site from its natural state of valleys and steep hillsides into acres of construction-ready flat pads. A variety of Belgard Diamond Pro blocks engineered by Anchor Wall Systems as well as Belgard’s Vertica Virtual Joint (VJ) and Planter blocks were chosen to make up the expansive segmental retaining wall system that created the buildable space.

PROJECT EXPERTS

To design and build the retaining wall, Baldwin & Sons chose to work with Geogrid Retaining Wall Systems, Inc., the largest segmental retaining wall installer in Southern California. Geogrid’s owner, Mike Stevenson, has more than 28 years’ experience, including pioneering some retaining wall technologies.

“Geogrid checked all the boxes in terms of the competency of their people, value-engineering and the products they were going to use. Their previous projects and references also gave us a high comfort level,” says Jose Capati, vice president of land development for Baldwin & Sons. “They were very proactive and responsive from design stage to construction and we are happy with the result of the collaboration.”

“There’s not much flat land left in Southern California, and there is a shortage of homes in Orange County, so installation of a retaining wall system is an investment in creating more property square footage to build homes on,” explains Stevenson. The project was broken into three phases: Portola Northwest, Portola Northeast, and Portola South. While the first two feature single family homes, the last phase saw construction of 313 single-family, 256 multi-family, and 58 affordable housing/mixed use dwellings. Portola North West and Portola South are completed. Phase 1 of Portola North East is substantially completed and Phase 2 is currently being worked on as well, with completion scheduled for December 2023.

Geogrid has an in-house design engineer, Matthew Merritt, P.E., of Red One Engineering, who exclusively designs the segmental retaining walls for their clients. For Portola Hills, the company designed and built walls comprising the entire perimeter of the project to develop “super pads,” acres of flat land for Baldwin to build on. Many of these walls reached up to 49 feet tall and 1,000 feet long.

“We were involved with each phase of the project early in the design process and that allowed us to collaborate with the owner, civil engineer, and geotechnical engineer on incorporating the various Belgard wall products into the project,” says Merritt. Weekly project meetings with the project management and engineering team also helped avoid issues during construction.

Among the main concerns for the project initially, according to Capati, were the poor soil quality of the site and the weather.  

OVERCOMING CHALLENGES

Early in the project, they started to experience landslides because there were failure planes in the soil being excavated. A failure plane is weak clay layer that causes instability. These thin layers are like grease which, once exposed, cause landslides as dirt and rock slip over them—especially during significant rainfall.  

“We worked with the geotechnical engineer on the global stability analysis and incorporating the Mirafi global stability geogrids into the wall design. Portola South had a long (100’+) and very strong geogrid for global stability. Portola NE had two walls incorporated into a large landslide buttress,” says Merritt. “We also worked with a shoring contractor to incorporate the Diamond Pro block facing over the shoring elements.”

Another natural element to contend with was the fact that the project was in a seismic area. In addressing global stability, the team designed a system of secondary geogrids, placed between the standard grid layers. A grid’s length is usually equal to 100 percent of wall height, so 40 feet long for a 40-foot-tall wall. At the Portola site, between every layer of standard-length grid and compacted fill was another, smaller grid of only 4 feet long. These strata of primary geogrid fabric, compacted fill, secondary grid, compacted fill, and so on provided the necessary additional stability in the seismic area.

There were also design requirements the team had to meet for the project, including the city’s demand that most of the walls be plantable. “For decades now, Southern California has required plantable walls so, over time, what passersby see is vegetation instead of standard concrete,” says Stevenson. Geogrid’s choice of Belgard plantable blocks gave them an advantage over the competition in the bidding process and, ultimately, gave Baldwin & Sons the maximum amount of space on which to build homes.  This is because Belgard’s Plantable system has an 8:1 batter and the competitor’s block has a 4:1 batter.

“The wall batter is a ratio of vertical feet to horizontal feet, so 8:1 means for every 8 feet vertical the wall slants backwards 1 foot so one foot of useable property is lost to the wall batter. The competition at 4:1 loses one foot every four feet of height, or two feet for every eight of height,” explained Merritt. “Using the various Belgard products provided the client with an additional 66,500 SF (1.5 acres) of usable land compared to using the competition at 4:1 batter.”

Geogrid designed the plantable walls to go up 4 feet, then back 6 inches, then repeated that to achieve the 8:1 batter. Providing plantable space every 4 feet high, without compromising buildable space, made it likely the vegetation would grow to cover the walls in a shorter amount of time than they would cover an 8-foot wall. All tall walls over 6 feet high were plantable.

“I have designed with Belgard wall products for over 10 years so I knew I could trust their block on such a large and critical project,” says Merritt. “We used the full line of Belgard products available to us to meet the needs of the owner and requirements of the City of Lake Forest. The result was great looking plantable and non-plantable walls that blend into the site, provide an excellent aesthetic and most importantly provide lasting confidence in their structural capabilities.”

CLOSING THOUGHT

In total, the project utilized Belgard’s Vertica®, Vertica Pro Stone Cut® Virtual Joint, Diamond Pro Stone Cut®, Diamond Pro Stone Cut Virtual Joint, Vertica Cap 8”, Vertica Cap 4”, and Belgard Plantable Unit.

“The fact that Belgard offers so many complementary products that we could use both as vertical and plantable walls was a huge asset,” says Stevenson. “The manufacture of the product was also outstanding. We were installing more than 1,000 square feet of block a day and they were always timely with manufacturing and delivery.”


for more information

Belgard, part of Oldcastle APG, offers a complete collection of paver and wall products for plazas, terraces, parking areas, roadways, rooftops, and retaining walls. Available in a range of styles, premium Belgard products have been found in the nation’s finest developments and award-winning commercial and retail properties since 1995. Oldcastle APG is part of CRH’s Building Products division. For more, visit belgardcommercial.com.



Modern Contractor Solutions, July 2021
Did you enjoy this article?
Subscribe to the FREE Digital Edition of Modern Contractor Solutions magazine.

BUTTON_ClickHere