You’ve got concrete ordered for tomorrow and a crew lined up. The customer has been waiting, and you’ve already moved the job once. Now the forecast looks questionable, and everyone wants to know what you’re going to do.

I manage paving and concrete projects, and I’ve been in that spot plenty of times. Moving the job can mean waiting weeks for another opening. You want to make it work, but you also have to be honest about whether you have enough time to do it properly.

Would you make the same call on a normal week?

That’s a question worth asking before you confirm the trucks.

When we’re behind, it’s easy to figure the schedule around everything going right. But a late truck or an equipment problem can eat up the little extra time you have. If a normal delay would put the pour in trouble, that needs to be part of the decision.

Maybe there’s a smaller section we can reasonably pour. Maybe an earlier start helps. Those options are worth discussing with the crew and GC, as long as the revised plan meets the job requirements.

“We really need to get it done” is understandable. It just doesn’t give us any more time before the rain.

LEAVE TIME TO FINISH

Say the first truck is coming at seven, and rain is showing around noon. You figure you can have the concrete down before then. Where will the finishers be at noon?

That needs to be part of the conversation before the order is confirmed. Talk with the people doing the work about how much time they need, what could slow them down, and how they’ll protect the concrete if conditions change.

The weather window has to cover the work that follows the last truck.

I want an honest estimate from the crew. If they need more time than the forecast appears to give us, I need to hear that while we can still change the plan. The schedule also has to account for the project’s requirements and the conditions on site.

GIVE EVERYONE A CLEAR ANSWER

Some of the stress comes from nobody knowing when the decision will be made.

Find out when the concrete supplier needs notice. Tell the crew and customer when you’ll update them, and make sure somebody owns that call.

If you’re still watching the forecast, say so, and give them a time you’ll check back. That’s more useful than leaving everyone wondering whether they should show up. Even after an evening decision, somebody needs to check for changes before the trucks leave.

When you do postpone, explain the actual concern.

“We can probably get the concrete placed, but I’m concerned we won’t have enough time to finish and protect it before the rain.”

The customer may still be frustrated. At least they understand what you’re looking at and why it matters. Let them know when you’ll have an update on rescheduling, even if you don’t have the new date yet.

DON’T JUDGE THE CALL ONLY BY WHAT HAPPENED

Sometimes you move a pour, and the rain misses you. That’s frustrating, especially when the customer points it out.

Keep a short note of what the forecast showed and why you made the call. Look back at whether the decision made sense with what you knew then.

Do the same when you go ahead and everything works out. Did the plan hold up, or did you catch a break? It’s worth knowing the difference before you use that job as the reason to take the same chance again.

You won’t get every weather call right. I don’t either. But before I confirm a pour, I want to be comfortable that the crew has enough time to do the job properly. If I’m counting on the weather holding off longer than expected, I need to take another look at the plan.


about the author

Rick Lapinsky manages commercial paving and concrete projects and is the founder of FieldCall, which helps contractors assess weather risk while keeping the final call in their hands. For more, visit www.myfieldcall.com.